2015-03-04 - 16702 - Spec - Purchasing Controls #purchaserequisitions

SPECIFICATIONS

16702.200 - Spec - Purchasing Controls


Purpose


Purchasing Controls

Admin Info


Purpose
Purchasing Controls
Requested By
Jeffrey Mau
Spec Created By
Laxman
Spec Created Date
03/04/2015
Spec QA by
Laxman
Objects
BUS2105
Document Status
WIP


Estimates



Sl.No
Activity
Estimation in Hours
1
Research
20
2
Documentation
08
3
Development/ Config
60
4
Unit test in DEV
24
5
Unit test in QUA
08
6
Other activity


TOTAL
120

References


Prior Tickets

[Provide links of prior associated Spec / Break Fix BOSS document(s)]

Documents
[Attach any document(s) received for the requirement(s)]



Spec Changes


[List the changes made to program after the approval of the original requirement along with the Date on which the change request was received and the name of the initiator]


Sl.
Change Details
Requested By
Requested On
Notes if any
01
Even if the dollar limit is less than 50k the VP should be copied in cc
Saravanan
04/24/2015

02
VP also notified along with requester that PO has been issued
Saravanan
04/24/2015

03
Short text (description) also required in the notification along with requester, price and vendor
Saravanan
04/24/2015

04
Single approval if user is assigned to different positions of same Purch group
Saravanan
04/24/2015

05
Only requester is notified when the PR is converted to PO
Jingsha
05/04/2015

06
Need to forward the header text to approver in the email notification
Jingsha
05/07/2015

07
Notification should go to all the prior appoveres if rejected
Jingsha
05/30/2015

08
PO PDF to requester if MRO PR is converted to PO
Jingsha
05/30/2015

09
Create new purchasing group for MRO-Canada and setup release strategy
Jingsha
06/23/2015

Functional Requirement


Purpose/WHY:

[Explain the purpose of the project and the reason why this requirement has come]

As per the business requirement these are changes required to the current workflow setup.
1. Tiered approval is required (instead of single approval) based on dollar limits.
2. Purchase requester needs a notification once the MRO PR is converted to PO.
3. Header text will forwarded to approver in the email notification to approve the purchase requisition. Header text will contain link. Then approver will open the document by click on the link.
4. Even if the dollar limit is less than 50K the VP should be copied in CC
5. Short text (description) also required in the notification along with requester, price and vendor
6. Single approval if user is assigned to different positions of the same Purch group.
7. Notification should go to all the prior approvers if PR is rejected.
8. PO PDF to requester if MRO PR is converted to PO.
9. Create new purchasing group for MRO-Canada and setup release strategy.


In Scope:

[List the activities to be included in scope]


Out of Scope:

[Out of scope activities]

Solution Summary


[Discuss this section with Requester and get approval prior to beginning work]

Modify the current workflow setup as per the document given below by New Era

Automated Requesitioning Process (Hycner - February 12 2015) FINAL.pdf


Workflow setup.jpg



1. Tiered approval is required (instead of single approval) based on dollar limits.

- Modify the current configuration from single approval to tiered approval as per the given document. If required need to modify the workflow setup also.

2. Purchase requester needs a notification once the MRO PR is converted to PO.

- To forward the email notification to requester when MRO PR is converted to PO setup a new email output. For this we need to modify the existing routine.

3. Header text will forwarded to approver in the email notification to approve the purchase requisition

- Need to enhance the sub type ZBUS2105

4. Even if the dollar limit is less than 50K the VP should be copied in CC

- Need to enhance the business object BUS 2105

5. Short text (description) also required in the notification along with requester, price and vendor

- Need to enhance the sub type ZBUS2105

6. Single approval if user is assigned to different positions of same Purch group.

- Modify the configuration accordingly

7. Notifications to all the prior approvers if PR is rejected.


8. PO PDF to requester when MRO PR is converted to PO.


9. Create new purchasing group for MRO-Canada and setup release strategy.



Test Plan

[List test scenarios/cases to be executed here]
Test ID
Test Scenario
Expected Results
MM001
Create the MRO purchase requisition and execute the workflow
Notifications for approval should go as per the document given by New Era
MM002
Convert MRO Purchase Req to purchase order
Email notification will be triggered and forwarded to PR requester and VP
MM003
Create the MRO purchase requisition and attach any document. Then execute the workflow
Attachment also should be forwarded to approver along with the notification

Solution Details


[Provide complete technical details for configuration or programming here]

.As advised by New Era modify the current workflow setup

Issues


[List Issues / Bugs identified in configuration or development]